FY 2023 Major Projects
Projects in Planning
Flint College of Innovation & Technology Building
Horace H. Rackham Educational Memorial
100 Farnsworth Street, Detroit Michigan
Hadley Family Recreation & Well-Being Center (Central Campus Recreation Building Replacement)
New Michigan Marching Band Practice Field
Michigan Medicine Childcare Facility
Projects in Progress
Bonisteel Boulevard Water Main and Road Reconstruction | Work started December 2022 with an estimated completion date of March 2024. Financing is from reserves and utilities reserves.
Center for Academic Innovation Leasehold Improvements | Work started October 2022 with an estimated completion date of September 2023. Financing is from tenant improvement allowance and reserves.
Chemistry Building and Willard H. Dow Laboratory East Campus Switching Station Upgrade | Work started November 2021 with an estimated completion date of September 2023. Financing is from utilities reserves.
Climate and Space Research Building Leinweber Space Innovation Laboratory Renovation | Work started February 2023 with an estimated completion date of March 2024. Financing is from the College of Engineering.
East University Chiller Plant Chiller Replacement | Work started December 2021 with an estimated completion date of September 2023. Financing is from utilities reserves.
Environmental and Water Resources Engineering Building and George Granger Brown Memorial Laboratories Civil and Environmental Engineering Project | Work started September 2022 with an estimated completion date of December 2023. Financing is from the College of Engineering.
Edward and Rosalie Ginsberg Building | Work started May 2023 with an estimated completion date of June 2025. Financing is from a gift.
Hadley Family Recreation & Well-Being Center (Central Campus Recreation Building Replacement) | Work started December 2022 with an estimated completion date of June 2025. Financing is from reserves and Student Life.
Hayward Street Geothermal Facility | Work started January 2023 with an estimated completion date of March 2025. Financing is from reserves.
Leinweber Computer Science and Information Building | Work started May 2022 with an estimated completion date of September 2025. Financing is from state capital appropriation, the Office of the Provost, the College of Engineering and the School of Information.
Medical Science Research Buildings I, II and III Installation of Backup Generators | Work started July 2021 with an estimated completion date of August 2023. Financing is from the Medical School.
Medical Science Unit I B and D Wings Renovation | Work started March 2023 with an estimated completion date of December 2025. Financing is from the Medical School.
Michigan Stadium Scoreboard Replacement | Work started August 2022 with an estimated completion date of December 2023. Financing is from the Athletic Department.
New North Campus Undergraduate Housing | Work started June 2022. As of February 2023 the project is paused. Financing is from Student Life.
New Building for the College Of Pharmacy | Work started February 2023 with an estimated completion date of December 2025. Financing is from reserves and gifts.
President’s Residence Infrastructure Renovation | Work started May 2022 with an estimated completion date of September 2023. Financing is from reserves.
Recreational Sports Fields Hubbard Road, North Campus | Work started June 2023 with an estimated completion date of December 2023. Financing is from Student Life.
University Of Michigan Health | Financing is from University of Michigan Health.
-
7300 West Joy Road, Dexter, Michigan Specialty Pharmacy Expansion | Work started June 2022 with an estimated completion date of September 2023.
-
Clinical Expansion Project 300 W. Michigan Avenue, Ypsilanti, Michigan | Work started January 2023 with an estimated completion date of December 2023. Financing is from tenant improvement allowance and University of Michigan Health.
-
Courtyard Infrastructure Improvements and Restoration | Work restarted December 2022 with an estimated completion date of March 2024. Financing is from reserves and utilities reserves.
-
D. Dan and Betty Kahn Health Care Pavilion | Work restarted May 2021 with an estimated completion date of June 2025.
-
W.K. Kellogg Eye Center and Brehm Tower Boiler and Hot Water Feed Interconnection | Work started May 2023 with an estimated completion date of December 2024. Financing is from utilities reserves and University of Michigan Health.
-
University Hospital and University Hospital South Clinical Pathology Laboratories | Work started January 2020 with an estimated completion date of December 2023.
-
University Hospital Electrical Substation Replacement | Work started July 2022 with an estimated completion date of September 2024.
-
University Hospital Pneumatic Tube Expansion | Work started September 2022 with an estimated completion date of June 2024.
Projects Completed
William W. Cook Legal Research Library and Hutchins Hall Exterior Repairs | Completed August 2022. Financed by the general fund.
Dean Road Transportation Facility | Completed December 2022. Financed by Logistics, Transportation & Parking.
Robben W. and Aldyth Fleming Administration Building Demolition | Completed November 2022. Financed by reserves.
Palmer Field Temporary Recreation Facility | Completed January 2023. Financed by reserves.
Harold T. and Vivian B. Shapiro Library Third Floor Renovation | Completed April 2023. Financed by gifts and the Office of the Provost.
A. Alfred Taubman Biomedical Science Research Building Vivarium Expansion | Completed October 2022. Financed by the Medical School.
University Of Michigan Health | Financed by University of Michigan Health.
-
Brighton Center for Specialty Care Shell Space Utilization for New Operating Rooms | Completed June 2023.
-
Brighton Center for Specialty Care Linear Accelerator Expansion | Competed June 2023.
-
Samuel and Jean Frankel Cardiovascular Center Positron Emission Tomography/Computed Tomography Scanner Project | Completed March 2023.
-
C.S Mott Children’s and Von Voigtlander Women’s Hospitals Emergency and Psychiatric Services Renovation | Completed March 2023.
-
Rogel Cancer Center Exterior Improvements | Completed July 2022. Financed by University of Michigan Health and the general fund.
-
University Hospital Air Handling Unit Replacement | Completed May 2023. Financed by insurance funds.